Purpose

This work instruction describes the process to replace a power jack for all versions of the E8 Centrifuge.

 

Required Equipment

  • Power Jack Cable Assembly; E8 (Part # 100525)
  • #1 Philips Screwdriver
     

Summary of Process

The procedure involves unplugging the unit, removing the rotor and base/motor assembly, and then disconnecting and replacing the power jack. The new power jack is wired in, and the unit is reassembled and tested to ensure proper functionality.

 